Date

Project Description

Requested By

Status

June 2007

Install graphing calculator interface in one of the Cook hall 1st floor multimedia stations.

Math Department

Waiting to hear what room they want it installed in and how it’s to be configured. The hardware and calculator are still on the shelf in the Engineering office.

January 2008

Testing wireless projector device in 107 Cook with Mike Steinfort as our “guinea pig”.

Mark Vogel

Todd installed the unit and is working with Mike. Unit has been working well but did lock up once on 3/17/08. Todd re-set it and we will continue to test.

March 2008

Specify flat panel displays for Winchester Alley that are “public proof”, secure and durable

Jim Vandokkumburg & Eric Mullen

Working on a solution/recommendation

March 2008

Add a secondary teaching control station in the MTEC computer lab to allow instruction from the back of the room.

George Waite

Working on a solution/recommendation

March 2008

Update MTEC Atrium multimedia system with Crestron control, twister removal, etc…

George Waite/Mark Vogel

Working on an upgrade design – Todd/Duane will install this summer.

 

March 2008

Would like to add an Elmo camera document station for Foreign Language instructors.

Cathy Noviskey

Gave her a price quote. Not sure who should purchase, etc. Talk to Vicki.

 

March 2008

I've just been approved to do a pilot with live, streaming video and audio/video capture in 108 Cook this summer. Janet has scheduled my two classes in the room and Patti has approved the research component. Next, I'll be getting back with Mark and Klaas about hardware and software.

 

Garry

Garret Brand

Nothing yet…

March 2008

Re-Start the process of getting the multimedia stations connected to the network so we can remotely manage, update, gather information, etc…from the units. This will GREATLY improve our ability to support the classroom.

Mark Vogel/Todd Torrey

Started the ball rolling with Bill – May 08

Restarted ball rolling with Donovan – March 09

March 2008

Cable channel UPS  wiring

·         CATV Amps

·         Hammer/Auto shutdown

·         Amanda/On-Hold

·         Avid’s (Huge Arrays, one monitor, Mikes cooling fan, auto shut down of WS)

 

Mark/Todd/Duane

Bruce has completed the power wiring to the racks. We can now begin re-working the power distribution in the racks.

March 2008

Update the ATC banquet rooms Crestron with projector control

Mark/Duane

Duane, work with Oene for wiring pathway + re-program the system.

March 2008

Figure out how to install an umbilical cord in the Enrollment Center classroom

Mark/Todd

Will need a custom configuration – Possible wall plate on east wall?   Complete 3/17/09

April 2008

239 Cook is a computer lab with a wall rack, and the computer video/audio feeds via twister back to the rack. They've been having some issues with it working lately, plus the RJ-45 jack is in the floor smack dab in the middle of the walkway. Do you mind if I run a VGA+audio to replace the cat5? There is a power pole near the workstation that should have room for the cable.

Todd/Mark

Evaluate system configuration this summer and re-wire/configure as nessesary.

Fall 2008: Replace MLS switcher with 5ip, got rid of twister, and added second computer input at back of lab. Cabling to instructors workstation still needs to be fixed.

April 2008

Modify power in older MM classrooms so Extron control system remains on.

Todd/Tim/Ben/Mark

Todd is looking at power distribution unit modification options. We will implement during summer maintenance.